[BPT][Process]about parallel activities

[BPT][Process]about parallel activities

  

Good Moring,

  Can I create parallel activities in runtime.

  ?https://www.outsystems.com/academy/lesson/908/parallel-activities/


 

 

Hi Hon,

I'm not sure where you want to go with your question, but I try to answer based on what you asked:

With Outsystems you have to define / create your process including the process steps (activities) in ServiceStudio and when your app is deployed you can create/run the activities in parallel.

Kind regards,

Remco Dekkinga

Hi Remco,

  Thank you very much.

>With Outsystems you have to define / create your process including the process steps (activities) in ServiceStudio >andwhen your app is deployed you can create/run the activities in parallel.

  I see it can run in parallel.

  In my case , I want to decide humanactivitiesin run time.  

  And Let them (humanactivities)  run in parallel.

  But I dont know how to.

 

Kind regards,

hon