After an upgrade in a Solution with BPT, I have several hundred activities that were resume with a new activity, and the old one remaing in the waiting state with Strikethrough over it. How can I find the activities that still remain in this "state".

Thank you,
Renato
Renato Santos wrote:
Hi,

After an upgrade in a Solution with BPT, I have several hundred activities that were resume with a new activity, and the old one remaing in the waiting state with Strikethrough over it. How can I find the activities that still remain in this "state".

Thank you,
Renato
 
Hi Renato,

Sorry for the late reply.

I believe you can find that information in the BPT data-model {Process_Upgrade} entity. The activities seen with a strikethrough in Service Center should be marked as Deleted.

 