Hi,
We have a number of processes that are dependent on dates, specifically we have Wait activities with 2-3 month timeouts.
What is the best way to test these processes without having to wait 2-3 months?
We think we may need some functionality to "skip" these waits, or maybe we need a different design pattern in our process, etc. we are not sure.
Any advice would be greatly appreciated.
Thank you,
Hello David,
You can create a site property (on service studio) and add in your flow, define what date you need wait (on service center):